Diagram showing construction flow

Construction starts in Cluster 1 (910s), goes to the 900s, then clockwise around the complex.

Posted in Uncategorized | 3 Comments

2nd construction meeting, Dec. 10, 2012

Wow, there’s a lot to tell here. Stonemark read through my summary of Monday’s meeting and made a few updates. Here’s the summary: Dorothy, Harold and Bob discussed three main items at the Dec. 10 construction meeting: 1. Scheduling of … Continue reading

Posted in Uncategorized | Tagged , , , | Leave a comment

Hello neighbors, this is our leak project blog

This “wcplrp” (West Campus Point Leak Remediation Project) blog is for residents to share their experiences with and questions/concerns about the ongoing construction, which began Nov. 5, 2012 and is slated to run through Nov. 4, 2013. I’ve posted Dorothy’s first week diary as a … Continue reading

Posted in Uncategorized | Leave a comment

Video of de-roofing, 3rd day in a cluster

[youtube=http://www.youtube.com/watch?v=6Nqn5MgvMDA] <www.youtube.com/watch?v=6Nqn5MgvMDA> (1:10 mins) The concrete tile parts of the old roofing are being removed in advance of the main re-roofing project; the new “titanium” brand roofing paper is installed as full interim waterproofing. This is what that process looks … Continue reading

Posted in Uncategorized | Leave a comment

1st video walkaround, 4 weeks in (5:06 mins)

Wednesday Dec. 5, early afternoon, 4 weeks into the LRP: trellis, deck and stucco work (both demo and repair) ongoing. Corrections to narrative: not a diesel electric generator, but yellow power station drawing from common power at pool, powering a … Continue reading

Posted in Uncategorized | Tagged , | 1 Comment

1st Construction Meeting, Nov. 30, 2012

Dorothy and Harold met with Bob Landegger for 2 hours on Friday afternoon. Items discussed: Turn-around time and contact chain when project decisions arise: Dorothy and Gail will be primary contacts, if unsure they will pass on to Gabriela, Harold … Continue reading

Posted in Uncategorized | Leave a comment

Sharing construction-free housing for tots & pets

At the Annual Meeting Cathy Weinberger offered to coordinate exchanges between anyone needing a quiet home to keep their small children or pets, and owners not yet under (or already done with) construction. I’ll suggest posting offers here, too, so … Continue reading

Posted in Uncategorized | 1 Comment

Days 3-5

Stucco removal in carports at ledger site.  Power (partial) washing of 911 – 914 .  More roofing material removal.  Titanium underlayment on 919 and 911 — 914. Day 4: a little bit of rain early, then “titanium” roofing paper applied.Day … Continue reading

Posted in Uncategorized | Leave a comment

Day 2

Roof tiles came off – no dropping of tiles into a bin below.  Tiles were lowered by means of a forklift with an extending arm and a bin attached to it.   Back trellis dismantled – they seem to be labeling … Continue reading

Posted in Uncategorized | Leave a comment

Day 1

Carport and upper deck trellises came down.  Courtyard tiles scored along  18” perimeter.  All drains plugged up for testing (and tested – 912 ended up with a leak in the livingroom ceiling).  They will now check INSIDE the homes for … Continue reading

Posted in Uncategorized | Leave a comment