Monthly Archives: January 2013

Stonemark’s Jan. 25 email re: week of Jan. 28

Next week’s expected construction activities are outlined as follows.  Because of ongoing rain, work will continue to focus on buttoning up the deck & deck door areas for those units already in progress.   Cluster / Units 901 through 919:  Demo … Continue reading

Posted in Uncategorized | Tagged , | Leave a comment

Tue Jan. 22 construction meeting notes

Window/door order: The windows for the 910s are now on site (900s due at end of Jan.), but the doors have been delayed substantially and are not expected until Feb. 21. W/D are being ordered in batches because of slight … Continue reading

Posted in Uncategorized | Tagged , , | Leave a comment

Jan. 10, 2013 (Thursday) Harold’s Construction Meeting notes

Marty Kim is co-managing with Bob Landegger until the project becomes more routinized. Right now we have a “perfect storm” of heavy rains, needing to develop procedures and solution details for various things (flashing, ledgers), ramping up delivery of materials (doors … Continue reading

Posted in Uncategorized | Tagged , , , , | 2 Comments

Jan. 14 “Anticipated Weekly Plan” from Stonemark

Jacklyn sent this on Jan. 11 (also as pdf): Week of January 14, 2013: Anticipated Construction Activities Dear WCP Homeowners, Work will continue as scheduled for already begun activities for all homes except for the following new tasks listed below. New … Continue reading

Posted in Uncategorized | 2 Comments

Serious Problems in First Cluster

Neighbors, These are only my observations – others may disagree with fact, or point of view.  Let me begin by noting that I believe that Gail is on top of this having spent a great deal of time discussing how … Continue reading

Posted in Uncategorized | 2 Comments