Monthly Archives: July 2013

July 10 Construction meeting notes

Overall process: one month deck & trellis work; one month door & window work; one month plaster & stucco work. Harold’s record for 930s: Deck & trellis work May 20-June 19. Demo June 7-13 mainly (week 4). Back windows/doors boxed June … Continue reading

Posted in Uncategorized | Leave a comment

Construction survival tips for 950s-970s

Here is Gabriela’s question to the WCP community list, followed by the responses. My own take is that the procedures have been substantially refined, and were getting a few final optimizing tweaks in the 930s, so that things will go … Continue reading

Posted in Uncategorized | Leave a comment

930s: Log of construction activities, weeks 4-7 (illustrated)

Week 4 (June 10-14) Entry courtyard tiles scored, then demo’d 2 days later. Very loud and dusty. You can get an impression of the sound in the video walk-by: http://youtu.be/hawqgtcBMIU. Back windows boxed, back patio cement demo’d around perimeter. All Stucco … Continue reading

Posted in Uncategorized | Leave a comment

July 8-12 Stonemark newsletter

I. Cluster/ Units 911-916:  Access Required All week. Contractors will be in & out of homes all week working on final tasks. Punch List Inspections have been scheduled for your cluster for July 8th & 9th between 8am to 3pm. … Continue reading

Posted in Uncategorized | Leave a comment

June 25 Construction meeting notes

Schedule update. 910s: Unfortunately, the final punch list will not close out this week. The contractor(s) have not completed their own confirmation that all work has been done to specifications (completion list). Bob can’t do his punch list (with the … Continue reading

Posted in Uncategorized | Leave a comment