July 8-12 Stonemark newsletter

I. Cluster/ Units 911-916:  Access Required All week.

  • Contractors will be in & out of homes all week working on final tasks.
  • Punch List Inspections have been scheduled for your cluster for July 8th & 9th between 8am to 3pm.
    Please make sure you respond and send us your punch list items for consideration before this date.

II. Cluster/ Units 901 through 909:  Access Required All week.

  • Contractors will be in & out of homes all week working on final tasks .
  • Punch List Inspections have been scheduled for your cluster for July 11th & 12th between 8am to 3pm.
    Please make sure you respond and send us your punch list items for consideration before this date.

III.  Cluster/ Units 921 through 928:  Access Required All Week.

  • Contractors are installing interior drywall, casing /trimwork /baseboard.  
  • Roofing work will stop for a couple weeks, and plastering will resume.  

IV. Cluster/ Units 931 through 938:  Access Required All Week.

  • Window & door replacements are in progress for the courtyards.  
  • Carport work is ongoing. Please continue to refrain from parking in your carport between 7:30am to 5pm.
  • Roof work is ongoing .

V. Cluster/ Units 941 through 947:   Access Required:  Monday, July 8

  • Mike with Mac’s Solar will be onsite Monday morning to drain down the solar panels. (If you have a disabled solar panel, pls disregard this message).
    • Access is required to utility room where the hot water heater & solar panel hook-up are located.  If your solar water heater (not control panel) is located in the garage, please ensure access to this is provided.  This work should not take more than a few minutes. The disconnection of your solar panel will not adversely affect your hot water supply.  
  • Plaster Demolition and roofing will begin.
  • Trellis work is ongoing. Please continue to refrain from parking in your carport between 7:30am to 5pm until Further Notice.
  • Deck work is ongoing: please do not lock the deadbolt on your deck door any longer.
  • Expect the first application of Tufflex waterproofing either late this week or early the week of the 15th. 
    • Courtyard demolition is complete.  

VI. Cluster/ Units 950s:   

  • As discussed at the Cluster meeting, exterior demolition work will likely begin the week of July 15th
  • Work will begin with demolition of the carport & deck trellises. 
  • Please make sure that all personal items are removed from your patios and decks by Monday July 8th in anticipation of work.   

Project Manager Martin Lee Kim will be on-site with the workers on Friday July 5. 

Best Wishes for a Happy & Safe 4th of July!!
Bob Landegger
Jacklyn Wolf

Advertisements

About hmarcuse

I've been an environmentalist since my college days in the 1970s (May 1977 Seabrook, New Hampshire occupation) , and am now a professor of German history at the University of California, Santa Barbara.
This entry was posted in Uncategorized. Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s