Tue Jan. 22 construction meeting notes

Window/door order: The windows for the 910s are now on site (900s due at end of Jan.), but the doors have been delayed substantially and are not expected until Feb. 21. W/D are being ordered in batches because of slight … Continue reading

Posted in Uncategorized | Tagged , , | Leave a comment

Jan. 10, 2013 (Thursday) Harold’s Construction Meeting notes

Marty Kim is co-managing with Bob Landegger until the project becomes more routinized. Right now we have a “perfect storm” of heavy rains, needing to develop procedures and solution details for various thingsĀ (flashing, ledgers), ramping up delivery of materials (doors … Continue reading